Palletizing machine with wood chips preparation

  • Palletizing machine with wood chips preparation
  • Palletizing machine with wood chips preparation
  • Palletizing machine with wood chips preparation
  • Palletizing machine with wood chips preparation
  • Palletizing machine with wood chips preparation
  • Palletizing machine with wood chips preparation
  • Palletizing machine with wood chips preparation
  • Palletizing machine with wood chips preparation

Description:

The project was divided into three construction phases:

 

I BA:

Steel construction with TKF – transfer

Steel construction at three levels with staircases and walkover to Phase II

 

II.BA:

Steel construction with dryer exit

Steel construction with two platform levels

 

III.BA:

Steel construction dryer input

Double leveled platform construction on top of the existing hall roof with all sides safety and cage ladder.

 

The tasks of AHP:

Making structural calculations for inspections including the details and information, which are important for the creation of the construction drawings.

Creation of the construction drawings (3-D) including the part lists, bolt lists and nc-data that are important for the fabrication of the units.

  • Location: Germany
  • Software used: Autodesk Advance Steel
  • Design office: AHP Konstruktionsbüro für Stahlbau