Bridge Hochalmbahn in Bruck at the Mur

  • Bridge Hochalmbahn in Bruck at the Mur
  • Bridge Hochalmbahn in Bruck at the Mur
  • Bridge Hochalmbahn in Bruck at the Mur
  • Bridge Hochalmbahn in Bruck at the Mur
  • Bridge Hochalmbahn in Bruck at the Mur
  • Bridge Hochalmbahn in Bruck at the Mur
  • Business issues: One challenge in this project were the cambered curves in all 3 axes with elliptical axis line and trapezoid section. Another challenge were the cutted plates in the arch, which have a different slope and which are adjusted to the three-dimensional cambered curves.

 

  • Solution: With Advance Steel we were able to put out the actual lengths of all sheet metal parts after having integrated cambered curves. Without a 3D-Software like Advance Steel the realisation of this project would not have been possible.

BENEFITS:

  • Benefit 1: 3D modelling
  • Benefit 2: automatic creating of workshop drawings
  • Benefit 3:  automatic creation of bills of material

 

  • Software used Advance Steel 2011
  • Company NCA Container Anlagenbau GmbH
  • Contracting authority: Land Steiermarkt
  • Location: Bruck, Austria
  • Dimensions: Span: 70 m; height of the steel arch: 32 m;
  • Specifications: Weight: approx. 380 tons; diameter of the rope: 56m
  • Description: The Bridge consists of a steel framework with a welded steel arch. The cantilever construction is carried by 22 ropes which are connected to the steel arch.